Earned Value Management (EVM) Tracker in Excel: CPI, SPI and EAC
- XLSX
- 13 KB
- Version 1.0
- English
- October 22, 2026
Ready to download
Editable Excel file
This sheet is also available in: العربية
Percent complete alone does not tell you where a project stands. You might be 50% done but have spent 60% of the budget, or be behind schedule without noticing.
Earned value ties cost, schedule and progress together in clear numbers. This sheet applies it to 25 activities: enter the budget, planned and actual percent and actual cost, and it calculates the indices and forecasts the final cost.
Who is it for?
- Project managers and planning engineers
- Contractors tracking profitability
- Consultants preparing monthly reports for the owner
What is inside the sheet?
- A table for twenty-five activities with PV, EV, CV, SV, CPI and SPI
- Automatic coloring of indices below 1
- Project indicators: CPI, SPI, EAC, ETC, VAC and TCPI
- Percent complete and percent spent
- Project status in one line
How to use it
- Enter the project name and status date.
- Enter the approved budget of each activity.
- Enter the planned percent to date from the schedule and the actual percent complete.
- Enter the actual cost of each activity and read the indicators.
Formulas used
PV = budget × planned %, EV = budget × actual %CPI = EV ÷ AC, SPI = EV ÷ PVEAC = BAC ÷ CPI, VAC = BAC − EACTCPI = (BAC − EV) ÷ (BAC − AC)
Worked example from the sheet itself
A villa project with a budget of 1,000,000 and seven activities:
- Planned value to date is 576,500, earned value 522,000 and actual cost 555,000.
- CPI = 0.94 (over budget) and SPI = 0.91 (behind schedule). The estimate at completion is 1,063,218, an expected overrun of 63,218, and the remaining work needs 1.07 efficiency to stay on budget.
Tips for best results
- Update the sheet at the same point each month so comparisons are fair.
- Measure progress from quantities actually done, not guesses.
- Start with the activities that have the lowest CPI; they drive the overrun.
Frequently asked questions
What is the difference between PV and EV?
PV is the value of work that should be done by now per the plan; EV is the value of work actually done at budget prices.
What does a TCPI above 1 mean?
You need better than usual efficiency on the rest of the project to finish within budget.
Does it suit any project type?
Yes, any project with a budget and schedule: construction, maintenance, IT and more.
Download the sheet
Press the download button at the top of the page to get the Excel file. It includes a full guide sheet, yellow input cells and formulas protected from accidental edits. The sheet is also available in Arabic from the language switcher.